Customer Case Study: Delivering Operational Scale without Compromising Evolving Timelines
Location: Coral Springs, FL
Roof System: Tile
Manufacturer: Westlake
Number of Buildings: 24
Total Installed Squares: 2,500
Unique Customer Requirements:
200 DAYS COMPRESSED TO 120 – When Connor Group requested an accelerated year-end completion, Reliable cut the original project timeline by 40% while maintaining installation standards.
SCALED RESOURCES TO MEET THE GOAL – We quickly deployed a second crew and divided the property into simultaneous work zones, significantly increasing production.
2,500 SQUARES DELIVERED ON DEADLINE – The large-scale tile replacement was completed in just 120 days on December 27, demonstrating our ability to adapt mid-project and execute at scale under aggressive timelines.
When Connor Group engaged Reliable Roofing to complete a 2,500-square tile replacement, we were initially looking at a 200-day timeframe based on the size and complexity of the property. Shortly after mobilizing, The Connor Group requested an expedited timetable, working towards a year-end completion, targeting 120 days. With that revised goal in place, we reevaluated our approach. To increase production, we added a second crew and divided the property so teams could work opposite sides simultaneously. This allowed us to meaningfully compress the schedule while maintaining consistent installation standards across the project. Reliable Roofing ultimately delivered the 2,500-square tile replacement in 120 days, completing the project on December 27, 2023.This project reflects our ability to adapt midstream, scale resources when needed, and execute large, complex tile replacements under accelerated timelines.